I am not sure that I can offer clarification on the committee papers, but the Government prepared a press release in response to assertions that were made by a member of the committee about the timescale. I confirm that that is not the timescale to which we are working.
I thank the committee for providing me with the opportunity to update it on the major transport projects portfolio. It has been a busy time for the projects, and significant works have been undertaken in recent months across all the projects that we will discuss.
First of all, I draw the committee’s attention to the announcement that was made on Monday this week, alerting bridge users to the fact that the Queensferry crossing will become a designated motorway from 1 February. That represents the latest successful milestone in a remarkable project. As members will be aware, the Queensferry crossing was opened in a phased manner to allow road users and local communities to familiarise themselves with the new road layout, while speed limits were gradually increased. Now that road users are familiar with the new environment and the speed limits, we feel that it is appropriate to implement the full managed crossing strategy and to designate the new crossing as a motorway. In effect, that will mean changes to the types of vehicles that can use the new bridge, with non-motorway traffic no longer being allowed access to the Queensferry crossing.
I came over the Queensferry crossing this morning, when the Forth road bridge was closed to high-sided vehicles, and to double-deckers in particular, including the buses that use the bridge as a public transport corridor. That is obviously one of the benefits of the replacement crossing. The change also provides a monumental opportunity for cross-Forth travel for all modes of transport. That will include the full opening of the public transport corridor—notwithstanding the wind issues that we have been experiencing—for buses, taxis and motorcycles up to 125cc, and it will allow pedestrians and cyclists to use the dedicated public transport links and the Forth road bridge.
In order to assist road users to understand the road and bridge layouts, an excellent road-user guide has been published this week and will be made widely available at libraries, petrol stations, bus and train stations and tourist information offices along the Forth corridor and across the east-central Scotland region. In addition, the guide has also been published online and is being promoted via social media.
The 70mph speed limit was implemented on the Queensferry crossing on 19 December. The phased approach to introducing final traffic arrangements on the new bridge has allowed the speed limit to be moved gradually from 40mph to 50mph, and now finally to 70mph. During the period, we have monitored the new structure so that the changes could be undertaken safely while allowing road users to become familiar with the network and layout.
Since opening, traffic volumes have generally returned to the previous levels that were seen on the Forth road bridge. Traffic flows improved as the speed limit was raised to 50mph, and early indications suggest that that is also the case with the increase to 70mph. An initial journey-time assessment has been undertaken for the Forth corridor between the M90 junction 2 at Admiralty, and the M9 junction 1A in both directions. The free-flow journey time for that route, since the transition to the 70mph limit, has typically been about nine to 10 minutes, which is a slight improvement on the journey times of around 10 to 11 minutes that were regularly observed prior to the raising of the speed limit. That may be a small improvement, and it is too early to say conclusively that journey times have improved significantly.
It is anticipated that there will be further improvements when the managed motorway is brought into full operation towards the end of this month. Traffic Scotland will continue to monitor traffic levels closely.
I remind the committee that the Queensferry crossing is a replacement crossing; it was not built to increase capacity, although it has that effect, given the nature of the existing bridge as a public transport corridor.
I will now provide the committee with an update on the Aberdeen western peripheral route Balmedie to Tipperty project, following the announcement on 15 January that Carillion Construction Ltd has filed for insolvency. Carillion Construction Ltd had a one third share in the AWPR joint venture that is responsible for delivering the construction phase of the AWPR project. As members of the committee will be aware, news of the insolvency has had a major impact on the construction industry.
On the Monday morning, after Carillion made its announcement, I had a phone call with David Mundell, the Secretary of State for Scotland, to reinforce our commitment to working with the United Kingdom Government on how best to mitigate the impact of the announcement. On Tuesday 16 January, I met high-level officials across Government and agencies to discuss key actions and to consider plans. Following that meeting, helplines were set up for employees and companies that might be affected by the liquidation of Carillion.
On 17 January, I had a constructive meeting with representatives of the Scottish Trades Union Congress and the Unite and GMB unions, and I assured them that we are doing all that we can to minimise job losses. I assure the committee that I will continue to be in close contact with the liquidators and the UK Government about the measures that they intend to put in place regarding private sector Network Rail and UK Government-backed contracts in order to secure completion of those contracts. I reiterated that the Scottish Government had been working to manage or eliminate risks associated with Carillion’s difficulties since July last year, and that we have contingency plans in place for all the affected contracts, including, of course, the AWPR. Should it be necessary, we stand ready to support affected employees through our partnership action for continuing employment initiative, which aims to minimise the time for which individuals are affected by redundancy.
We recognise that it is a very worrying time for Carillion workers; my thoughts are with those who have been affected by the announcement. However, we have been working closely with the Aberdeen Roads Ltd consortium to understand the impact of the announcement on people who have been employed by Carillion. I understand that steps have been taken for Carillion personnel who were due to remain on the project to transfer to the remaining joint-venture partners for the project. Unlike contracts for other projects elsewhere in the UK that members might have seen reported, when the gates were, essentially, locked after the announcement, the non-profit-distributing form of contract that has been used for the AWPR caters for a number of different scenarios, including a situation such as this one with Carillion. As a result, I am pleased to confirm that, unlike some other projects, work on this project will continue.
I also confirm that the announcement generates no direct additional costs to the Scottish Government, because each partner of Aberdeen Roads Ltd and its construction joint venture are jointly and severally liable for the performance of the contract. We have been advised by Aberdeen Roads Ltd that the remaining construction partners, Balfour Beatty and Galliford Try, will now take the necessary steps to deliver jointly the remainder of the project.
I previously advised the committee that the project was due to open in the spring: work is well advanced. In fact, there is a road along the 58km length of the project—you can drive on it now and I intend to drive on it in the next two or three weeks. However, although the situation with Carillion does not in itself affect project delivery timescales, members will appreciate that, given the scale of the project, there exists the potential for loss of confidence in the supply chain: indeed, I have been contacted by one party in the supply chain.
It is important that we now take the necessary time to work closely with ARL to identify any impacts on delivery. We will then consider what we can do to mitigate any problems that might arise as a consequence of that. That might take some weeks to determine, but I will be happy to provide further updates to the committee in due course.
It continues to be a busy period for the A9 dualling programme. Work is continuing along the route, and road users are already benefiting from the new dualled stretch between Kincraig and Dalraddy, which was opened to traffic at the end of September last year. The construction contract for the second section between Luncarty and the Pass of Birnam is expected to be awarded during the first half of this year. The procurement of an A9 advance works framework is also under way.
At the same time, design work on the remaining nine schemes of the dualling programme is well advanced, with over 90 per cent of the dualling programme having reached “preferred route” status. Over the past couple of months, we have published draft orders for four dualling schemes representing about 30 of the 80 miles that are to be dualled. Draft orders were published for the Killiecrankie to Glen Garry project at the end of November, and those for Pitlochry to Killiecrankie, Glen Garry to Dalwhinnine and Dalwhinnine to Crubenmore were all published in December. There will be no let-up in the design work and we expect publication of draft orders for further dualling schemes over the coming months.
The project is not just about building a road; it is part of an ambitious dualling programme. We have developed the Academy9 education and training programme, which has the goal of getting local pupils ready for the local jobs that the A9 dualling programme will create.
10:15
Design work is also well under way for dualling the A96 from Inverness to Aberdeen. We have published draft orders on the 31km Inverness to Nairn section, which includes the Nairn bypass, and later this year we expect to identify the preferred option for the 46km section between Hardmuir and Fochabers. Route options assessment work is also under way on the 42km section between east of Huntly and Aberdeen, and we expect to present the options that are under consideration to the public later this year for feedback. A preferred option is to be identified in 2019.
Following the opening of the Raith underpass in February 2017, the M8 bundle project fully opened to traffic on 1 June. Significant journey time savings have been experienced across the central Scotland motorway network. Road users are enjoying peak journey time savings of 20 minutes on the M8 and 15 minutes at the Raith interchange, as well as more reliable journey times, enhanced safety and reduced emissions. The on-going finishing works are expected to be completed in the coming months.
I am aware that the committee is likely to have some questions about Prestwick airport, which I will be happy to discuss in more detail, but I restate that the Government’s wish remains for the airport to grow into the successful and vibrant business that we believe it can be. As members might know, the airport’s annual report and accounts were published on 15 December. They contain some positive statistics. Passenger numbers rose by 8 per cent, aircraft movements increased by 8.2 per cent and turnover increased from £11.5 million to £13.6 million, which is an increase of about 18 per cent. Operating losses were £7.8 million for the 12-month trading period, compared with £8.7 million for the previous 12-month trading period. In addition, there has been increased revenue from military activity—gross revenue in that area has increased by 33 per cent over three years.
However, we have always acknowledged that there is no quick fix, and that a sustained effort over a number of years will be required. I am keeping developments under close review.
I thank the committee for the opportunity to update it, and I will be happy to answer any questions that members have.