Thank you, convener. I am grateful for the opportunity to come along and provide the committee with further information on the progress of the Queensferry crossing and the other projects—the Aberdeen western peripheral route, A9 dualling, A96 dualling and the M8, M73 and M74 improvement projects. My update will be brief: I will then welcome any questions for me, David, Michael, Alasdair and Lawrence.
On 20 June, I was pleased to advise the committee that the Queensferry crossing will open to traffic on Wednesday 30 August. That followed confirmation from the FCBC that it would be in a position to open the crossing to traffic for the first time on 30 August, due to the excellent progress that has been made over previous weeks.
I am pleased to update members on the significant progress that has continued on the north approach roads and on the Queensferry crossing itself since my appearance at the committee on 31 May. I will start with the crossing. The installation of wind barriers is close to completion along the full length of the structure. The Alimak hoists—or “Ally McCoists” as they have been called—have been removed from the tower top to deck level on the south and north towers. Those were the lifts at each tower that were used by workers throughout the construction of the crossing. Preparations are currently under way to remove the hoist on the centre tower.
On the north side, the final construction works and paving of the Ferrytoll junction and slip roads are progressing to completion as planned. Final surfacing of the junction took place on the weekend of 3 and 4 June and finishing works are currently in progress.
Between now and the opening of the crossing, our focus will be on completing the waterproofing, final road surfacing and all activities on the towers and cables above road level.
On 20 June, I was also delighted to be able to announce the opportunity for the public to take part in the Queensferry crossing experience—a once-in-a-lifetime opportunity for 50,000 people to cross the Queensferry crossing on foot before it becomes part of the motorway network. Members will agree that the project has really captured the public imagination, and there has been a fantastic demand to take part in the Queensferry crossing experience?. The evidence of that demand is the more than 195,000 entries that we have received since the ballot opened on 20 June. However, the ballot will not close until 12 noon on 5 July, so there is still plenty of time for those who wish to apply. Everyone entering has a chance of being one of the 50,000 people to walk over the new bridge. I encourage people to submit an entry so that they, too, might share in the experience. It is clear to me and to those who are involved in the crossing’s construction that the people of Scotland have taken the bridge to their hearts. There is a great deal of anticipation and excitement about the opening celebrations, as can be seen in the excellent public reaction to the Queensferry crossing experience. We will not be able to accommodate everyone, but I am sure that it will be a hugely enjoyable event for all involved.
On the other major projects, following the opening of the M74 Raith underpass in February, the new and improved M8, M73 and M74 progressively opened during spring and were fully opened to traffic on 1 June 2017. As is normal with such projects, final landscaping, finishing and snagging works will be ongoing until the autumn, although that should not affect peak traffic flows.
Since those new roads fully opened more than three weeks ago, the contractor has been focusing its resources on the installation of motorway gantries and signage, and those works are being undertaken overnight in order to avoid impact on road users. There has already been substantial progress. Almost immediately after opening, the benefits of the £500 million project became apparent. The significant new road capacity has already started to deliver economic benefits right across Scotland, due to the strategic nature of that part of the motorway network.
On the AWPR and the Balmedie to Tipperty project, extensive activity has been taking place across the sites over recent months. The Stonehaven southbound slip road opened in April 2017, bringing early benefits to the people of Stonehaven by taking long-distance traffic away from the town. Earthwork operations have also recommenced, which has allowed the contractor to continue with the Balmedie to Tipperty section so that it will be completed at the same time as the remainder of the project.
A significant milestone on the project was reached when the 1,000th beam was lifted into place at the new Goval junction on 21 June. We still need another 183 beams, and it is anticipated that they will be in place by the autumn. Elsewhere, road surfacing and foundation works are continuing apace. The new major bridge over the River Dee is taking shape, with work on the deck progressing well.
Transport Scotland officials and I are continuing to work together with the contractor, Aberdeen Roads Limited, to deliver the benefits of the project to the people of the north-east at the earliest possible opportunity.
It has also been a busy period on the A9 dualling programme. With the Kincraig to Dalraddy section currently under construction and the Luncarty to Pass of Birnam project now in procurement, a significant amount of construction work is under way and being planned. On the Kincraig to Dalraddy project, traffic was switched on to the newly upgraded carriageway last weekend to allow the final phase of works to be undertaken, including the removal of remaining temporary works and the completion of site-wide finishing and landscaping works. That section is on target to be fully open to traffic during summer 2017, as planned.
Following a successful industry day on 10 April, procurement has commenced on the next section of the A9 dualling programme, with the publication of the contract notice for the Luncarty to Pass of Birnam section of the dualling. Six prequalification submissions have been received, and the bidding process is expected to commence in July 2017. Advanced works are scheduled to start on site later this year, with the main construction contract expected in spring 2018. Design work on the remaining nine schemes of the A9 dualling programme is progressing well, with more than 90 per cent of the programme having now reached preferred route status.
Design work is well under way on the A96 dualling programme, too. Last November we published draft orders on the 31km Inverness to Nairn section, which includes the Nairn bypass. Last week we presented to local communities at a series of exhibitions the options that are under consideration for the 46km section between Hardmuir and Fochabers. More than 1,800 members of the public attended the exhibitions, and the vital feedback that the engineers received will inform further design and assessment work as we look forward to identifying a preferred route option for that section next year. We also expect to start route options assessment work on the section between east of Huntly and Aberdeen later this summer, following the procurement of design consultants.
The fruits of the Government’s commitment to infrastructure investment are now becoming plain for all to see, with projects such as the M8 bundle reaching completion. The scale of our ambition to deliver sustainable economic growth for Scotland can be seen right across the portfolio of projects, from the Queensferry crossing to the A9 and A96 dualling programmes. In delivering those projects, we have supported jobs and enabled businesses to grow right across the country. The A9 and A96 dualling programmes will further augment that successful approach.
I thank the committee for the opportunity to update you on the projects, and I am happy to try and answer any questions that the committee may have.