Edinburgh to Glasgow Improvement Programme

Topical Question Time

Tuesday 13 June 2017 Meeting of the Parliament Questions 12 contributions · 5 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

12 contributions
Jamie Greene Con West Scotland
link

To ask the Scottish Government what the final cost will be of the Edinburgh Glasgow improvement programme. (S5T-00586)

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

As I recently informed the Parliament, Network Rail has confirmed a further delay to the route electrification. We await further advice from Network Rail on the costs arising from the delay. Tomorrow, Mark Carne, the chief executive of Network Rail, will be in front of the Rural Economy and Connectivity Committee, of which Mr Greene is a member.

Jamie Greene Con West Scotland
link

The Edinburgh to Glasgow improvement programme was supposed to cost the taxpayer £742 million. However, just under a year ago it was reported that the cost had risen by £32 million. A further delay was announced, for the replacement of faulty electrical equipment, which might incur additional staffing costs.

Does the minister expect further increases in the cost of the improvement programme? More important, does he think that the additional costs will impact other rail projects or rail funding in general?

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

I thank Jamie Greene for the question and the tone in which he asked it. He will be aware that the responsibility for delivery of the project is Network Rail’s; Transport Scotland and the Scottish Government are the client and the funder. We have a funding ceiling within which we must work, and I do not expect it to be breached. I assume that that was the member’s question.

There has been a further delay. We will continue to have discussions with Network Rail, and I defer to Network Rail on the potential cost increases; it will have to get back to us on that. From a Scottish Government perspective, the most recent report on cost increases is the independent report from EY, which the committee has had sight of.

The problem is shared with the United Kingdom Government. Network Rail is a reclassified body under the Department for Transport, and the UK Government faces issues with Network Rail that are similar to those that the Scottish Government is facing. Now that the UK Government has been appointed—Cabinet members have certainly been appointed—I am keen to sit down with the railway minister in the UK Government as soon as possible to find some sort of shared solution. It is not acceptable that we, as the client, fund major projects for which Network Rail—which is responsible for delivery—is not accountable to this Government or this Parliament.

Jamie Greene Con West Scotland
link

The minister is passing the buck to Network Rail, to some extent. Surely, as the minister in charge of transport in Scotland, he must have some oversight and can share with Parliament the costs of the project.

We know that electric trains will not be delivered on the Edinburgh to Glasgow line until October, nearly a year after the 2016 deadline. There have been a range of problems, including components breaking down, poor project management, unforeseen corrective action and a delay in the energisation of the overhead cables. A spokesman for the Scottish Government has said that that is “wholly unacceptable”.

What assurances can the minister give to passengers in Scotland, who have already suffered significant disruption on the line and must now wait potentially until the autumn for electric trains to be in operation? Does he agree that that is unacceptable?

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

Of course I agree that that is unacceptable, but I take issue with one or two things that Jamie Greene said. I am sure that he does not expect me, as the transport minister, to be literally on the wires and lines, delivering the project. It is being delivered by Network Rail. We have a responsibility as the funder—we are the client—but the project is being delivered by Network Rail, which is a reclassified body under the UK Government’s Department for Transport.

Any delay in a project is unacceptable. I informed the committee—no doubt, under the member’s questioning—that we expected electric services to come on to the route in July this year but that it is now going to be October, which is extremely disappointing. However, let me make a comparison. In some projects south of the border, there have been delays of not months but years—four years, in the case of the trans-Pennine electrification. We are in a better position.

I agree that it is wholly unacceptable that Network Rail continues to say to me that it is unable to deliver the project despite our having provided the funding as the client and funder.

To reassure passengers, we have a project board that is helping to flush out some of the issues much earlier than we would have had sight of them before. My commitment to Parliament is to continue to keep it and the relevant committee updated whenever I get that information from Network Rail.

I would welcome a discussion with parties across the chamber. Even if they do not agree with the full devolution of Network Rail—I respect that that might be their position—I ask them to at least think about the devolution of infrastructure projects, because it is unacceptable that we fund these projects yet the accountability remains with Network Rail as a reclassified body under the Department for Transport.

John Mason SNP Glasgow Shettleston
link

Will the minister confirm that the original cost of EGIP was quite a lot higher and that the idea of running longer trains less frequently means that there have been huge savings on signalling as well as less congestion, which I imagine is also better for the environment?

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

Yes, there have been cost savings not only on this project but on some others. However, I reiterate that that does not take away from the fact that we have seen a cost increase from our revised estimates, which has come about because Network Rail failed to notice some circumstances that it should have been able to foresee.

We will wait for Network Rail to give a further update on what further delay there may be on EGIP that may potentially lead to a cost increase. We are not letting Network Rail off the hook. Having said that, I am confident that the many railway projects that we are looking to deliver in control period 5 can be delivered within the funding ceiling to which we have committed.

There have been savings not just on EGIP but on other projects. However, that does not take away from the fact that this is disappointing news and Network Rail should be held to account not just by the Department for Transport but by this Parliament and this Government.

Neil Bibby Lab West Scotland
link

The Associated Society of Locomotive Engineers and Firemen—the train drivers’ union, ASLEF—says that EGIP has been mismanaged and has lacked political leadership from both Network Rail and the Scottish Government. As the Scottish Government is ultimately responsible for the project, despite the minister perhaps trying to suggest otherwise, does he accept that there has been a failure of political leadership on EGIP from the start? What will he do now to reassure the workforce, the passengers and the taxpayers that the Scottish Government should be trusted any longer with meeting the railway infrastructure needs of this country?

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

That question is beyond ludicrous for a number of reasons. EGIP has already delivered on many occasions. In December 2010, there was the electrification of Haymarket tunnel, and we took political leadership on that. In December 2013, the transformed Haymarket station opened to passengers on time and on budget as part of EGIP. In May 2014, there was the electrification of the Glasgow to Cumbernauld line—Neil Bibby forgot to mention that. In May 2015, we had the Haymarket to Inverkeithing resignalling—the member completely forgot to mention that. In December 2016, the Edinburgh Gateway rail-tram interchange opened to all passengers. Of course, the member forgot to mention all of that.

EGIP has achieved many of its milestones, and we have funded the achievement of those milestones—Neil Bibby should recognise that. If the member wants examples of political leadership on the railways, on top of EGIP, I can say that we delivered the Borders railway, the Airdrie to Bathgate link and electrification of the Cumbernauld line. A project that affects the member’s constituency is the Paisley corridor improvements. There have been many other rail projects, as well.

I will take no lessons from Neil Bibby when it comes to the management of our railways. I suggest that he look to his own Labour colleague, the former United Kingdom transport minister, Tom Harris, who said:

“The Scottish Government is responsible for the strategic direction and funding of the Scottish rail network, but this responsibility cannot be properly exercised while Network Rail remains answerable to the UK Government.”

He added that Reform Scotland, the think tank that he was working with at the time,

“believes that Network Rail in Scotland should be fully accountable to the Scottish Government, and that means it must be devolved.”

That is from somebody who was a transport minister in a UK Labour Government. I suggest to Neil Bibby that, instead of carping from the sidelines, he should take some expert advice on how to manage our railways.

Liam Kerr Con North East Scotland
link

People will be incredibly frustrated about the delay, not least because the drip, drip of information prevents anyone from taking full responsibility. Will the minister tell Parliament on what date he was informed of the potential delays to the project? Is he willing to publish minutes of all the meetings in which the delay was discussed?

Humza Yousaf SNP The Minister for Transport and the Islands · Glasgow Pollok
link

On the documentation about the delay, I have a letter from Mark Carne that was sent to me on 25 May, which I have written to the committee’s convener about. I will discuss with my officials whether a copy of that letter of 25 May can be published.

I share Liam Kerr’s and the public’s frustration about

“the drip, drip of information”

that we tend to get from Network Rail. As I continue to say, Network Rail is ultimately accountable to the UK Government, under the Department for Transport, as a reclassified body. I would like a conversation with Mr Kerr and members across the chamber about how we can rebalance the situation and ensure that Network Rail is accountable to this Parliament and this Government.

On the main part of the member’s question, I will look into whether the latest letter that I received from Mark Carne can be released.

Motions, questions and votes

Linked from this item of the Official Report
  1. Time for Reflection Time for reflection · 2
  2. Business Motion Business motions · 1
  3. Oath Procedure · 2
  4. Educational Institute of Scotland (Industrial Action) Questions · 14
  5. Edinburgh to Glasgow Improvement Programme Questions · 12
  6. Independent Advisory Group on Hate Crime, Prejudice and Community Cohesion Statement · 29
  7. Greenhouse Gas Inventory 2015 Statement · 35
  8. Human Trafficking and Exploitation Debate · 29
  9. Decision Time Decision time · 2
  10. Freedom of Information (Scotland) Act 2002 Members’ business · 38

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.