Thank you for the opportunity to update the committee. I will provide a brief update, and then I will welcome questions for me, David Climie, Michael Martin or Sally Cox.
On 29 March I advised the committee that the Queensferry crossing is now forecast to open to traffic between mid-July and the end of August, depending on weather conditions. That followed FCBC advising us that a May 2017 opening date was no longer achievable due to the effects of the weather, particularly wind, beyond those that it foresaw in June 2016. At that time, all members agreed that the safety and quality of the construction work should be the guiding principles in determining the programme to completion.
Both Transport Scotland and I continue to stress to FCBC that the continued focus on maintaining health and safety is our top priority, and I know that it is at the forefront of everything that it does.
I am pleased to update you on the significant progress that has continued on the north approach roads and the Queensferry crossing since my previous appearance at the committee, on 29 March, and since the last written update, which you mentioned, on 29 April. I went to the site on 19 May to see for myself the progress that was being made in the favourable weather conditions on that day—in fact, there was not a breath of wind at the top of the towers, which I am told is extremely unusual. I was hugely impressed by the progress that is being made on all the project’s key activities.
I am pleased to inform the committee—although you may already be aware of this—that all the tower frames have now been completely removed. The committee will recall that that activity was significantly affected from the start of the year, due to the lower than expected number of weather windows required to complete their removal. The removal of the under deck falsework has also been completed, as FCBC has taken advantage of the available weather windows in April and May. All the expansion joints have now been installed and the final deck concrete pours on the south approach viaduct have been completed.
The installation of wind barriers is nearing completion along the full length of the Queensferry crossing. They are an important design feature that will deliver a significant benefit to the travelling public. Members should think about the times when the existing Forth road bridge has to be closed to high-sided vehicles during high winds.
Waterproofing and road surfacing is continuing on the deck of the Queensferry crossing as planned. FCBC continues to progress the finishing works relating to the stay cables, such as guide pipes, dampers, deviators, and tension rings.
On the south side, the M90 approach road and the A90 public transport link are ready for tie-in and use when required. On the north side, the construction of the Ferrytoll junction is nearing completion and the Ferrytoll park and ride construction is complete, with the bus circulatory area now open.
As I confirmed to the committee on 29 March, the overall project cost to the taxpayer remains in the range of £1.325 billion to £1.35 billion, securing £0.25 billion of savings released since the construction started.
Community relations and public engagement continue to be hugely positive, and the project continues to attract a great deal of interest from a variety of stakeholders, including the general public, schools, colleges, universities, industry, international visitors and the media. The successful schools programme has attracted well over 20,000 school pupils from throughout Scotland in just four academic years, and the project exhibition at the dedicated contact and education centre has attracted well over 20,000 visitors. The project team continues to regularly provide presentations, which have been attended by more than 30,000 people, all of whom have been interested in hearing more about the project and the latest in the construction of the crossing.
The overall outreach and education programme has now attracted well over 70,000 individuals across all activities. Those activities will continue into the future and ensure that there is a lasting educational legacy from the project that, we hope, will ensure that future generations are inspired by the innovations of this world-class project and learn more about the science, technology, engineering, arts and mathematics that relate to it.
As members can imagine, public interest has also increased as construction has progressed. The public are now increasingly interested in how they can be part of celebrations to commemorate the completion and opening of this iconic structure. The project team has been considering the full range of options available to ensure that the public have the appropriate opportunity to celebrate the completion and opening of this world-class bridge. In the coming weeks, FCBC will provide Transport Scotland with an update on its programme to open the Queensferry crossing to traffic. Following that, announcements will be made regarding the opening celebrations that are planned for the crossing.
The Queensferry crossing remains on schedule to open to traffic between mid-July and the end of August 2017. As I have said before, the FCBC consortium continues to strive for the earliest possible date for opening to traffic. I also assure the committee that everyone who is involved in the project remains fully focused on completing it to the high quality that has been achieved so far and—just as important—as safely as possible. As Michael Martin mentioned to me recently, health and safety have no finishing line.
I am happy to try to answer any questions that the committee might have for me, David Climie, Michael Martin or Sally Cox.