Thank you very much, convener, and thanks to the committee for the chance to provide an update. At the last discussion that we had, committee members made it clear that they would like to be kept updated as frequently as possible and to take cognisance of any emerging issues, which is why I asked to come back to the committee. In particular, I will mention the Forth crossing—I know that members will hear about that subsequently—and the Aberdeen western peripheral route, but I will also mention where we are with most of our transport projects. It has been a busy time and significant works have been undertaken across all projects over recent months.
I will start with the AWPR. Since we last had a discussion about the 58km Balmedie to Tipperty project site, further progress has been made during 2016 and early 2017. I advised the committee previously that phase 1 of the project at the Aberdeen airport site opened in August last year, ahead of the contractor’s planned autumn target, and it is already being used and providing benefit to local people. In November last year, the contractor, Aberdeen Roads Ltd, advised us that it was unable to complete the Balmedie to Tipperty section by spring this year as originally planned—it is seasonally affected work. I alerted the committee to that change in December and I would like to provide a brief update on the progress that the contractor has made since then.
The Stonehaven southbound slip roads are expected to open in spring this year, which will bring early benefits to the people of Stonehaven by taking long-distance traffic away from the town. At the major bridge over the River Dee, the south pier is now complete and the north pier is in progress. Once the north pier is completed, the works to install the bridge deck will commence. Those works, which will include the slip forming of the concrete deck using a balanced cantilever approach, are due to begin by late spring. Road surfacing works recommenced last week in the southern section and the road foundation works are due to recommence this week. The fast-approaching spring season will also see the recommencement of the remaining earthwork operations.
There was some discussion and some press activity in the media last night about utilities, and it is worth mentioning that the project is unusual in as far as we were well aware of the pressure on utilities. Therefore, I asked all the utility providers to come to a meeting in advance of the contract being let so that we could discuss the ability to ensure that utility diversions, where necessary, were undertaken as smoothly as possible. That was an exceptional action; we have not done that in any other project. There are elements of commercial discussions with the contractor that I cannot divulge but, in addition, it is true to say that we have helped out with one or two substantial utility diversions—one in particular—at the contractor’s request. I will not go into the details but, at the request of the contractor, I wrote to the utility provider—not a public utility provider—to help out. Utilities will always be a major feature of such contracts.
As I notified the committee in December, there was a delay in relation to completing the Balmedie to Tipperty section but, despite the revised programme for Balmedie to Tipperty, our advisers have independently confirmed that the overall programme of delivery for the works by winter 2017-18 remains achievable. There will be challenges with that, as there are with all successful major projects.
Sound project management and, of course, sufficient resourcing by the contractor are required in addition to a willingness to resolve any issues between the parties in a sensible way. We undertake discussions on those things, as we do in all major contracts. They can sometimes result in tensions, of course, but we and the contractor are trying to do everything that we can to ensure that we complete the overall project on time.
In relation to Balmedie to Tipperty or any other delays, I think that I talked last time about whether a penalty was paid by the contractor, as that issue arose. It is worth repeating that that is not how it works; the contractor just does not receive any money. It will receive money for the airport section, which I mentioned earlier, as it is in use. Essentially, the penalty is that the contractor does not receive funding.
To conclude on the AWPR, Transport Scotland and I continue to work together with ARL to deliver the benefits of the project as soon as possible.
I will try not to anticipate too much of what members will hear from those who are involved in the Queensferry crossing, but I am sure that members will have seen that the final deck closure was completed on 3 February. Members will hear more evidence later about the progress that has been made, but I can say that things such as the waterproofing of the deck surface, the surfacing of the deck to take traffic, and work on the wind barriers are now being undertaken. Members will hear more about that work later, so I will move on to other projects.
Design work is well under way on the 11 road schemes that make up the 80 miles of the A9 dualling programme, which is one of the biggest transport infrastructure projects in Scotland’s history. Members might be aware that some residents of Kindallachan, Guay and Dowally have had concerns about some of the proposed options for dualling, on the ground that there would be negative impacts on the villages and their properties. The preferred route for that section was made public in December, and the online option was chosen, but residents remain concerned. In fact, they made representations in the public meeting after the Cabinet meeting in Pitlochry on 6 February. I spoke to residents, and members of Transport Scotland’s senior management team subsequently spoke to residents by telephone on 7 February to address concerns.
Residents of Birnam and Dunkeld remain in discussion with Transport Scotland on a co-creative process to capture community input into the route options design and assessment. We envisage that commencing after the local government elections in May to allow further progress towards identifying a preferred option.
On 31 January, the academy 9 programme launched a Scottish credit and qualifications framework module that will assist teachers who are involved in science, technology, engineering and mathematics to raise awareness of the A9 dualling programme in the areas of engineering, ecology, geology and sustainability. The academy 9 glow blog, which recently went live, features extensive material on the A9 programme for use by teachers and pupils. We look forward to supporting its use in schools across the length of the A9 in the coming years.
On the Kincraig to Dalraddy section of the A9 dualling specifically, traffic is already using the southbound carriageway, which some members might be familiar with. We remain on schedule to fully open the 7.5km stretch this summer to improve the safety of the route and provide better access to and from the Highlands.
A prior information notice—or PIN—for the construction contract for the 9.5km section between Luncarty and Birnam has now been published, and we hope to hold an industry day in the coming weeks to discuss the scheme with potential bidders. Preparatory works to facilitate that construction will begin later this year, and the main works contract is scheduled to commence in early 2018.
Design work continues apace across the rest of the route between Perth and Inverness, and a series of exhibitions are under way, which allow local communities to view the preferred routes for the lengthy 24km section between Dalraddy and Slochd and the 16km Crubenmore to Kincraig scheme. That is a further 40km of the A9 dualling programme.
Finally on the A9, work is under way to identify contractors to carry out a series of advance works across the entire A9 route in preparation for future construction. It is expected that the opportunities will be of particular interest to small and medium-sized businesses, including locally based businesses that would like to be part of that innovative and ambitious programme.
Our other big programme is, of course, the A96 dualling. There has been a contract notice for design work. The estimated prices for the two projects—they can be only estimates at the early stages of both projects, given that many contracts are still to be let—were similar, at around £3 billion.
A contract notice for the design work on the 26-mile stretch of the A96 from east of Huntly to Aberdeen, also known as the eastern section, was published on 24 January. That major contract marks a further milestone on the road towards the dualling of the A96, with all the investment and improvements that that will bring to the north-east and the Highlands. Our timescale for that is 2030, with the A9 being done by 2025.
Transport Scotland has also completed the development and assessment of the preferred option for the dualling of the 31km stretch of the A96 from Inverness to Nairn, including the Nairn bypass section, and it published draft orders for the scheme on 29 November for formal comment. The objection period ran for nine weeks, ending on 31 January.
Effective engagement with affected parties is a key part of the statutory process and it has been my experience that the more discussion that we have in the earlier stages of the process, the smoother the rest of the process will become. In many cases, that means that we can enjoy the support of those affected parties. As with all projects of that nature, we will engage directly with the objectors to resolve objections. I have spoken to some local members of the Scottish Parliament who have raised issues about the project. Only when the objectors have come forward will we be able to see whether a public local inquiry will be required to consider the objections that we have received and that have not been withdrawn. Ultimately, ministers will consider the outcome of all the consultations and objections that have been raised, including the recommendations of independent reporters, if that happens.
The objections that we have received so far are being assessed. However, in the event that we cannot resolve them all, we expect that a public local inquiry will happen late this year or early next year.
On the M8/M73/M74 motorway improvements project, the focus of construction has now shifted to completing the various structures across the project. We opened the 560m Raith underpass to traffic on 16 February. I do not know whether the committee has had a chance to look at it but it is an impressive development. It provides a direct link from the A725 Bellshill bypass to the A725 East Kilbride expressway. We have had substantial feedback from local people about the benefits that it has brought them. The development has received positive media coverage and is delivering benefits to the users of the A725.
The full benefits of the interchange will not be obtained until the works on the M74 are complete. We have now reached the stage of construction at which it is necessary to connect the new offline infrastructure, which is now almost complete, with the existing online road network. There is a significant height difference there, which is why we have had to put in place a 10-week diversion that is projected to add an average of 10 minutes’ delay. That is unavoidable at this stage of the project but we are now two or three weeks into that 10-week period. Although there have been delays, the diversion has been effective. The diversion route allows the tie-in of the new M8 motorway. Traffic on surrounding roads has been heavier but the diversion itself is performing well and officials continue to work closely with the Scottish Roads Partnership to ensure that traffic management measures are removed at the earliest opportunity, when it is safe to do so.
The last time that I came to the committee, members, including Mike Rumbles, expressed interest in the Laurencekirk bypass. That project is being taken forward by my colleague Humza Yousaf. The committee will have received an update after our previous discussion, so I will just say one or two words about that.
We announced the £24 million package for the design and construction of the new grade-separated junction at Laurencekirk. That was part of a package of additional investment alongside the Aberdeen city region deal. Transport Scotland appointed design consultants for the scheme in September, and is taking forward the next stage of design development for the junction improvement, which is the options assessment. Thereafter it will proceed through the relevant statutory procedures.
The on-going essential design and assessment process to identify the preferred junction layout is programmed to be completed in 2018. The detailed assessment of the preferred option will follow that, culminating in 2019 with publication of the draft orders for formal comment. Obviously there is still a lot of development work to be carried out but we will continue to push through the preparation stages to deliver the scheme as soon as possible. That will deliver improved road safety and economic benefits to road users and the local community in the wider north-east.
With that, convener, I conclude my remarks and thank the committee again for the opportunity to provide an update. I am happy to take questions on any of the issues.