Good morning. I will pick up on the question about the A9 and the A96. In general terms, the aims are still to dual the A9 by 2025 and the A96 by 2030, and we are planning on that basis.
The progress report mentions the £35 million contract for the Kincraig to Dalraddy section, which is on site, progressing well and due to complete in the summer of 2017. We recently saw a switchover on to the new carriageway for the majority of that section, and work is now under way to upgrade the existing carriageway.
As far as the more general work on the A9 programme is concerned, a considerable amount of planning and development work is being undertaken on the remaining seven sections that need to be developed. We are focusing on a number of areas, the first of which is identifying an appropriate route, taking into account environmental impact, buildability and cost. Statutory and consultation processes will be undertaken on each of those as we progress.
In a wider sense, considerable effort is also being put into discussions on how we procure and how we fund the remaining sections and the options that are available to us. It is a long-term programme, and circumstances can change quite significantly from where we are now to 2025, so we need a cogent strategy to get us from A to B, and that is what we are currently working through.
The options that we are considering—whether to use public capital, revenue finance or a mix of both—are being explored at this point. The other aspect of the development work and planning work that is important here is to understand the impact of such a large programme of works on the market and to engage with the market on market capacity.
The A96 is a longer-term programme, and at the moment we are focused on statutory process, particularly around the Inverness to Nairn section at the western end of the route, but the same planning and route selection processes are being gone through.
As far as the approach that is being taken with the A9 is concerned, I would like to highlight that the headline numbers that are reported on both programmes are in the order of £3 billion. We have recently engaged a challenge group, which is made up of experts from within the industry, to challenge our assumptions about the nature of the dualling project and the junctions strategy, as well as the estimates that we got. We will be able to firm up on those estimates only once route selection has been identified across all seven sections, when we will be able to take the design to a further stage, but that work is in hand.