I believe so. I do not find anything wrong with the approach that FETA took to managing its forward programme of work. It followed a risk-based approach, which is commonly used for asset management purposes.
Official Report · Committee
Forth Road Bridge Closure
Speakers
Choose an MSP to read only their contributions- Scott Lees Transport Scotland 51
- Jim Eadie SNP 38
- Richard Hornby Arup 35
- Mark Arndt Amey 29
- John Scott Con 26
- David Stewart Lab 19
- Siobhan McMahon Lab 18
- Adam Ingram SNP 11
- John Russell Amey 10
- Clare Adamson SNP 10
- Wayne Hindshaw Transport Scotland 6
- Colin Clark Fairhurst 6
- Mike MacKenzie SNP 5
The record
264 contributions · showing 201–264I put the same question to each of the witnesses. Mr Clark, do you have a view?
It is a difficult question for me to answer. We were one of several consultants working on the bridge, so I was not party to all the information that FETA had at the time.
You do not feel able to answer the question.
I do not feel that I can answer it.
Right. Mr Hindshaw?
I have reviewed the evidence and the information in the evidence pack. The scheme appeared fourth or fifth in the list of FETA’s priorities. My view is that, based on the evidence that was presented in the Fairhurst report and at the workshop, it was tolerable and appropriate for FETA to look for a more cost-effective and less disruptive solution. The solution that was presented at the workshop was clearly not fully developed and any consultant who was appointed would have looked to review it. Had it gone forward from the contract notice, a consultant might well not have taken forward the workshop recommendation—they could have come up with something different. That is what I find to be most likely.
The decision to take forward the work on a slower programme, as FETA did, was appropriate. It is interesting to note that FETA never brought the matter to us as a safety-critical piece of work that urgently needed funding beyond the capital grant that we gave it at the time. I feel that that is germane to a lot of the arguments because, some years later, when additional funds were needed urgently to take forward work on the cable band bolts, my predecessor was more than willing to listen and to act on that.
We have debated what would have happened if the works had been taken forward, which is an interesting concept. We also need to consider what would have happened if FETA had asked Transport Scotland for additional money to do those works and had presented evidence that persuaded us that they were urgent and needed doing.
I will bring in John Scott once I have heard a response from each of the panellists.
Obviously, I can comment factually only on the period after June 2015, when Amey became involved. However, based on what I have seen, the assessment report identified that the area was not overstressed. That was independently validated by another consultant. All the inspection records to date indicated there to be no perceived problems at that area. On that basis, the decision that FETA made seems proportionate.
As an ex-FETA employee in senior management, I will probably say that FETA made the right decision, based on the information that was provided by the report, which was that that element was not overstressed. We took forward the work on an overstressed element—the bracket. That was agreed and put forward. I think that the decision was correct.
We are slightly prejudging what the study would have come up with. At the end of the study, the consultant might well have recommended exactly the local strengthening of the overstressed element that has been undertaken, rather than the wholesale replacement of the link.
My question was whether, given the information that was available, the decision that was taken by FETA was a reasonable one.
I would agree with John Russell here. There was no evidence of distress in the elements of the link below. The localised strengthening that has been undertaken was proportionate.
I note the consensus; nonetheless, I wish to ask Fairhurst and Colin Clark in particular about the threats to the future
“structural integrity of the bridge”,
as outlined and identified in 2009 and 2010. Why use those words if you do not mean them?
My question was going to be, and probably remains, whether you believe that Transport Scotland engineers, or indeed the Scottish Government, understood the threat. When engineers tell you that there is a threat to the bridge’s future structural integrity, I would have thought—call me old fashioned—that that bumps things up the priority list.
I do not mean to be horrid about this, but you are all saying that the risk analysis techniques that were used were absolutely fine. The bridge and the member failed, so will there be a future re-evaluation of those risk analysis techniques, given that they did not work?
Who wants to tackle that?
I was talking about FETA’s procedures. It was FETA’s bridge until last June. It was not Scottish Government engineers who looked at the proposal; it was FETA engineers. They decided on what proceeded or not.
Perhaps Mr Hornby could expand on that answer.
The evidence that was presented in 2010 was that there was overstressing of particular elements, and a wholesale replacement was the answer. Some scratching of heads was done. People said, “Okay, we have many other issues with this bridge.” The immediate structural integrity question that was posed by Fairhurst and the independent checker was that the particular elements at the very top of the linkage were the ones that were suspect and which needed to be addressed. Those have now been addressed. It has taken five years for them to be addressed, but they are on stream now, with completion anticipated in the next month or so.
On that evidence, and without any signs of distress elsewhere, if we were looking for things to do on the bridge, we would not have started by saying that we needed to take out the thing in its entirety on the basis of the immediate risks that threatened. The element that was identified as being at structural risk and as representing a structural problem that had safety implications has been repaired and strengthened.
Given your knowledge, would you accept that Fairhurst’s assessment of the elements that need replaced was the correct one?
On the basis of no distress being observed elsewhere, that was the correct assessment at that time.
We were due to finish this evidence session at 12 o’clock. Given the importance of the issue, and as Siobhan McMahon has some questions, I will allow it to overrun. I am keen that you do not feel constrained by the time, Siobhan—please ask your questions as you normally would.
Mr Lees, you mentioned the £10.5 million toll income. The figures from the FETA board on the grant funding after the tolls show that, in 2007-08, capital and revenue totalled £8 million. Could you explain that?
12:00
If you could just bear with me, I have misplaced the document that contains the funding levels. Here we are. Did you ask about 2008-09?
No, 2007-08. The tolls had just come to an end, and what I am trying to get to is whether revenue from the tolls was still coming in or whether, for that year, FETA simply received £8 million in grant funding.
I have a document that summarises the FETA accounts. In 2008-09, there was no income from the tolls—
Sorry, it was 2007-08.
In 2007-08, toll income was £10.2 million.
So the £8 million would have been on top of the toll revenue, is that correct?
The £8 million for—
The £8 million that was given in grant funding to FETA—£4.5 million capital and £3.5 million revenue.
That was probably for a particular scheme. Would that have been for the A8000?
There was probably, and still is, some residue for the old A8000, which is now the B800, upgrade and the M90 spur. FETA was involved in the funding, because, when the Forth Estuary Transport Authority Order 2002 was introduced, there was scope for the money from tolls to go not just to the operation and maintenance of the bridge, but to other projects to alleviate congestion over the Forth, such as park-and-ride schemes and road linkages on either side. The A8000 scheme was one of those and involved a fair bit of cost.
With the tolls coming off in February, there was the residue for the rest of that financial year. Some of that would have been included in the figures, which is where you are going. There was an amount of money on the revenue side to keep staff paid from early February to the end of the financial year. Similarly on capital, there was a residue of works to be taken forward without the toll money.
That explains that point.
In 2014-15, the capital money went down to £1.7 million. Since, as we have discussed, the bridge is older, the traffic flow continues to increase and the tonnage and HGV numbers have increased, it seems odd that the capital grant to FETA is £1.7 million compared to its high of £8.7 million. What are the reasons for that? I understand that the contract was taken over in 2015, but what were the reasons for such a drop in the capital funding in 2014-15?
I believe, and Wayne Hindshaw can correct me if I am wrong, that FETA had capital reserves and was asked to use them instead of—
As the committee will be aware, Ms Nicholson—is it Ms Nicholson?
You can call me whatever. It is McMahon, but I answer to anything.
I am sorry—my apologies.
Do not worry.
FETA had considerable capital reserves. The intention of the bill was that, on the dissolution of FETA, the liabilities and assets would pass to the Scottish ministers. It was agreed that FETA would use some of its capital reserve to fund some projects and draw down its reserves in lieu of receiving capital grant from the Scottish Government.
I have not got the exact figures on what we gave them that year. The total grant—revenue and capital—in that year was £6.82 million, but the capital side was reduced so that FETA drew on its reserves.
I presume that that would have been normal practice?
It was. A condition in the grant letters, back to the days when Transport Scotland provided the grant, was that, should FETA not have spent all the money it had been given, it could carry it over, add it to its reserves and use it for the maintenance of the bridge.
For a number of years, FETA carried considerable amounts of capital reserves. At one time, the reserves ran into the tens of millions of pounds but, slowly, over the past seven or eight years, they have been drawn down. At the end of the period when all the actuarial work has been done, the hand back to the Scottish ministers will be about £3.2 million to £3.4 million. It still had reserves to take forward works.
If you need specific details on the amounts of reserves, the breakdown is in the pack that Scott Lees has given to the committee or they can be provided.
That was helpful. Thank you very much. To return to the programme for the maintenance and the upgrading work on the bridge, what is the year-on-year budget for that work? Can it be fully funded by Transport Scotland?
We took over the FETA programme, and it has been handed over to Amey. Perhaps Mark Arndt could advise on the scale of that and the schemes that we are doing.
We have announced the budgets for the following year. They are reasonably healthy. We are confident that we can fund the bridge’s needs, and we are committed to doing that.
I ask Mark Arndt to explain this year’s budget and the on-going works.
The budget from 1 April 2016 for this financial year is about £14.5 million. We have set out a prioritised list of schemes. There is a balance between routine and cyclic maintenance and what FETA formerly called capital projects. During mobilisation, we obviously had the FETA 10-year investment plan, and we have taken cognisance of that. We inform that with our own engineering decisions on matters that come up, such as the truss end links, and they will feature in the programme.
Other capital works that we have on-going or are programmed for this year include the motorisation of the gantry system—the cradle below the bridge that allows us to traverse along it—and the installation of a new gantry system. That will very much speed up access. As we have said, access to the component in question is very difficult, and the new gantry will aid that access significantly. Other capital works programmes are associated with the suspended span underdeck access platforms. The members who were out yesterday will have walked along the mesh panel system. Those are coming towards their life expiry date, so there is a scheme to replace them with a more modern system.
Now you tell us.Laughter.
Your experience was very enjoyable, I am sure. You can see the Sala wire—the safety line—in the photos. It is used when you walk along the bottom to get to the truss end links. It is 23 or 24 years old. That is getting replaced right now onsite. It was not unsafe, but all such components reach their expiry and safety critical components are essential.
There is a scheme to replace the south anchorage storage facility that was demolished as part of the cable inspection works. There is also the on-going routine cyclic maintenance, as I have said, to jack up the joints that, over time, drop down slightly and give the repetitive de-duh, de-duh effect. That work happens throughout the year.
I cannot narrow down the work to four or five schemes because there are the best part of 100 activities in the programme. They are all assigned their own budgetary requirements and taken through the approvals process with Transport Scotland.
We have spoken at length about how FETA came to prioritise works, so you do not have to go back over that, but do you use a similar process or is it an entirely different process?
I am not sure what process FETA went through, in all honesty. Our process is to take account of the capital programme produced by FETA, look at the basis of the defects on the bridge, the need for access, improvements in technology and suchlike, and on that basis, we make an informed decision and put that to Transport Scotland in the format of an annual programme that demonstrates how the money is allocated to each scheme and the delivery programme. Some schemes obviously do not get delivered in a single year and take a couple of years to progress.
For example, maintenance painting was a FETA scheme and we are looking at it, but we need to trial it and do it in a phased manner because access and systems in marine environments need to be trialled. The response is proportionate, but we go through a regimented and formal procedure so that it is submitted for approval by the dates that are dictated by our contract with Transport Scotland and then subsequently taken forward.
Have the projects that FETA established in its capital plan been adopted or did you start from scratch?
We have honoured all on-going contracts, which leads me back to the gantry motorisation and bracket strengthening work, which was fully honoured and taken forward. As I said, like John Russell and the team, 95 per cent of the people are still there so the capital plan has not been discarded by any manner of means. It is a co-ordinated effort and we have set out succinctly and in a structured manner for approval how the budget is to be spent that year.
I presume—you can correct me if I am wrong—that you would not adopt everything, because no one would. You would look at your own priorities to see how they are going. In your own plans for the year, regardless of the unfortunate position that you were left in at the end of last year, you would have looked at the truss to see what you could have done. Was there a plan to do anything with those? We have been through what was happening with FETA, what it had decided and how it went against that, but was doing that in any of your plans?
As I have said before, we were taking forward the strengthening of the member that was identified as overstressed. The member that failed was not overstressed. Such things take time. We are still in the midst of the bracket-strengthening work. There might have been a review and things might have been looked at but it would not be appropriate for me to say just now whether they would. That is the honest answer.
But they were not. When you bid for the contract that you took over, you would have talked about works to be done when you got the contract. You would have identified your priorities and that was not one of them.
No. You have to remember that this is a major suspension bridge. It would not have been prudent to discard all the prioritisation of work that had already been done by an experienced team. You have to take the best of both worlds, learn from that, and bring in any other engineering knowledge that you can to inform your work. That is the approach that we took.
Are there any final questions?
link
I want to go back to David Stewart’s question. Mr Lees, you talked about the decision in December 2011 to review the capital projects. I understand that FETA undertook a risk analysis that was based on a number of areas with the safety and structural integrity of the bridge at the heart of what they were deciding. Was that risk analysis robust and was there any independent accreditation of the process that FETA went through at that stage?
I believe that it was robust. I do not know the answer to the second part of your question about whether it was verified, but the rigour in the governance would have come from FETA’s board. The bridgemaster would have prepared a report and asked for a number of actions at the end of the report. I assume that the board would have applied rigorous governance at a board meeting, then consented to the approach.
I go back to something that I said before. I have high regard for the FETA team. They knew what they were doing. They were good. Thankfully, the majority of those staff are still with us and are continuing to do a good job on this significantly difficult incident that we are dealing with.
link
Mr Russell, were you involved in that process?
Fortunately not. I remember the guys taking it away and doing several nights’ work on it; they did not enjoy the process. You can check with Barry Colford and Chris Tracey next week but, if memory serves, there were independent people involved. My guess would be Atkins but I cannot remember the exact detail. Just going through the figures kept them awake for several nights over the weekend, but they came up with the right results in the end and we managed to get a priority list and go forward with that.
I want to get my head around this properly. Mr Hornby, in your view, what caused the failure of the member was essentially the seizing in place of the pin and the fact that it was not able to move freely over a period of years, which led to the failure of the member and the break in it.
Correct.
And, to be fair, that could not reasonably have been foreseen.
There was no mechanism to check that the pin was moving.
Thank you for that succinct answer, Mr Hornby.
As the witnesses have indicated that they have no further points to make, it only remains for me to thank you for your attendance this morning. I think that I speak for all members when I say that we have been impressed with the quality of your evidence; you have set a high standard for the rest of the inquiry. Thank you.
12:15 Meeting suspended.
12:19 On resuming—
In this meeting
Everything on 20 Jan 2016 →- 10:00 Decision on Taking Business in Private Procedure · 1
- 10:00 Forth Road Bridge Closure Committee business · 264
- 12:00 Subordinate Legislation Subordinate legislation · 1
- 12:00 Subordinate Legislation Subordinate legislation · 1
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.