Written Question · S2W-19932 · Session 2
Why the Dalkeith northern bypass is now regarded as urgent and what evidence the Executive has that the current estimate of £40 million rep…
The question
To ask the Scottish Executive why the Dalkeith northern bypass is now regarded as urgent and what evidence the Executive has that the current estimate of £40 million represents best value for taxpayers in terms of transport options for the area, given that the multi-modal appraisal promised by it following the strategic roads review in 1999 has never been carried out.
The answer
The Strategic Roads Review decision intended that a number of schemes, including the A68 Dalkeith Bypass, should be brought forward after the schemes approved for construction had been completed. That stage has now been reached.
The Dalkeith bypass is being taken forward as part of a range of measures to improve accessibility to the Borders, including the promotion of a new rail link. The economic benefits of the bypass have been reassessed and continue to indicate a positive return on proposed investment.
The Dalkeith bypass is being taken forward as part of a range of measures to improve accessibility to the Borders, including the promotion of a new rail link. The economic benefits of the bypass have been reassessed and continue to indicate a positive return on proposed investment.
In the Official Report
No contribution in the Official Report cites S2W-19932 by reference.