SPCB Written Question · S2W-01611 · Session 2
What the overspend on the new Parliament building has been in each year since 1999 and which budget sub-head has met this overspend.
The question
To ask the Presiding Officer what the overspend on the new Parliament building has been in each year since 1999 and which budget sub-head has met this overspend.
The answer
Expenditure on the new Parliament building at Holyrood has been less than the Scottish Parliamentary Corporate Body’s (SPCB) approved annual budget for each financial year since the commencement of the project. There has therefore been no overspend against budget. The expenditure, net of reclaimable VAT, for each year is shown in the table below.
Year | £ Million
1999-2000 | 13.7
2001-01 | 27.1
2001-02 | 44.4
Year | £ Million
1999-2000 | 13.7
2001-01 | 27.1
2001-02 | 44.4